ECRMinor· Normal· ECR-1970-0228
Re-balance rotor assembly to ISO 1940 G2.5
Open engineering change in flight.
- Site
- Mooresville (US)
- Source
- Customer
- Owner
- S. Hassan
- Created
- 2/24/1969 · 57.7y ago
Jira tickets
Linked Jira issues
Cross-reference this change with one or more Jira issues. Imported Aras items can be auto-linked from the Connections page.
No Jira issues linked yet.
Tip: save your Jira Site URL in Connections to make these chips clickable.
Stage timeline
E0EBOM/Article change request
Initiation · Requester
25d
1 stay
E1EBOM/Article change approval🔒
Initiation · BG QA / Plant QA
28d
1 stay
E2Design package validated
EBOM · Engineering / Design
20d
1 stay
E3RFQ -> Initial sample request (FIS)
EBOM · Purchasing
12d
1 stay
E4Initial samples qualified -> FP
EBOM · Purchasing / Quality
15d
1 stay
E5EBOM validated for execution🔒
EBOM · Engineering / R&D BG
23d
1 stay
E6BG Methods initiation (BaaN)
MBOM · BG Methods
13d
1 stay
E7Plant Methods MBOM creation
MBOM · Plant Methods
11d
1 stay
E8Industrialization
MBOM · Plant Methods
20d
1 stay
E9MBOM release🔒
MBOM · Plant Quality
13d
1 stay
E10PPAP / Supplier qualification
Article · Quality / Purchasing
15d
1 stay
E11RLNP — Run rate / Pre-series🔒current
Article · Production
57.1y
1 stay
E12Series started
Article · Production
—
E13Closure & archiving
Closed · Change Manager
—